MOF
Streetcar Update: December 20, 2013
Yesterday, Cincinnati City Council voted to restart streetcar construction after a three week pause to audit the project. Here’s what’s coming up over the next two weeks:
Thursday, Dec. 26
- Rail delivery on Elm Street (Findlay to McMicken). Elm Street will be closed from 11am-4pm.
Friday, Dec. 27 & Saturday, Dec. 28
- Rail installation resumes north of Findlay Market
Monday, Dec. 30
- Rebar installation resumes on Elm Street, north of Findlay Market.
- Building wood forms for trackwork resumes north of Findlay Market, with concrete placement expected Jan. 2-3.
- Work resumes on traffic signals and poles for overhead power.
- Water main work resumes on Walnut & Main streets.
Thursday, Jan. 2
- Excavation for trackwork resumes at Findlay & Elm streets.
Streetcar Weekly Update: November 18, 2013
For the week of November 18, 2013, the streetcar will continue installation of rail and proceed with track construction near Findlay Market. The Maintenance & Operations Facility site continues a two-week process of installing new sewers as backfilling nears completion. As part of the city’s construction contract, the project is also involved with repairing public utilities. Here’s what to expect:
- Concrete base work for the track will continue on Elm Street between 12th and Green streets.
- Rail installation will continue on Elm Street between 15th and Wade streets. Work will start on Elm between Wade and Green streets.
- Replacement of granite pavers will continue on Elm Street.
- Existing pavement removal will start on Elm Street near Green Street.
- Pier work for the building foundation will start at the Maintenance & Operations Facility. (Piers anchor deep into sturdy soil to support the weight of the building, making it structurally sound.)
- Backfilling for the Maintenance & Operations Facility will continue at Henry and Race streets.
PUBLIC UTILITY IMPROVEMENTS AS PART OF STREETCAR CONSTRUCTION:
- Water main installation will continue on Walnut Street near 8th Street. Work will start on Main Street near 4th Street.
- Installation of conduit (tubing for electrical wires) for traffic signals will continue on Race Street near Findlay Street. Work will start on 2nd Street near Main Street.
- New sewer installation will continue on Race Street near 13th Street. Work will start on Race near 14th Street.
- Storm sewer work will continue at the Maintenance & Operations Facility; and on Race Street near Findlay Street.
- Duke Energy will be doing underground gas work on Main Street between 4th and 5th streets; and on Race Street near Green and Elder streets.
- Duke will also do underground electrical work on 12th Street near Vine and Race streets.
- Telecom work will take place on Elm Street near Green Street; on Race Street near Green and Liberty streets; on Race near 14th and 15th streets; and on Race near 12th Street.
- Exploratory digging for utilities will continue on Walnut Street between 6th and 9th streets.
Streetcar Weekly Update: November 11, 2013
For the week of November 11, 2013, the streetcar will continue installation of rail and proceed with track construction near Findlay Market. The Maintenance & Operations Facility site will begin a two-week process of installing new sewers as backfilling nears completion. As part of the city’s construction contract, the project is also involved with repairing public utilities. Here’s what to expect:
- Rail delivery and installation will continue on Elm Street, between 15th and Wade streets.
- Concrete base work for the track will continue on Elm Street, between 12th and Wade streets.
- Existing pavement removal will start on Elm Street, between Wade and Green streets.
- Backfilling for the Maintenance & Operations Facility will continue at Henry & Race streets.
- Storm sewer work will continue in the Maintenance & Operations Facility site; and on Race Street near Findlay Street.
- Replacement of granite pavers will continue on Elm Street, in front of Music Hall.
- The Elm Street entrance to Washington Park Garage will be open again.
PUBLIC UTILITY IMPROVEMENTS AS PART OF STREETCAR CONSTRUCTION:
- New sewer installation will continue on Elm Street, near Elder and Findlay streets; and on Race Street, between Central Parkway and 13th Street.
- Sewer work will take place on Main Street and 8th Street in the Central Business District and on Henry Street and Race Street in Over-the-Rhine.
- Water main installation will continue on Walnut Street, between 9th Street and Central Parkway. Work will start further down Walnut, between 7th and 9th streets; and on Elm, near Elder and Findlay.
- Conduit installation for traffic signals (tubing for electrical wires) will resume on Race Street, near Elder and Green streets.
- Underground gas work will be performed by Duke Energy on Main Street near 4th Street; on Race Street near Findlay Street; and on Race Street, between Liberty and Green streets.
- Underground electrical work will also be conducted by Duke on 12th Street between Vine and Race streets.
- Telecomm work will occur on Elm Street, from Green to Wade streets; on Race Street, between 14th and 15th streets; on Race at Green; and on Race Street near Central Parkway.
- Exploratory digging for utilities will start on 2nd Street, between Main and Walnut streets.
Streetcar Weekly Update: November 4, 2013
For the week of November 4, 2013, the streetcar will have of a lot of highly visible progress on both the trackwork and at the Maintenance & Operations Facility site. As part of the city’s construction contract, the project is also involved with repairing public utilities. Here’s what to expect:
- Rail delivery and installation will start on Elm Street between 14th and 15th streets.
- Concrete base work for the track will continue on Elm Street between 12th and Wade streets.
- Replacement of the cobblestones will take place on the east half of Elm Street.
- Storm sewer installation, backfilling, and pavement removal for the Maintenance & Operations Facility will continue at Henry and Race streets.
PUBLIC UTILITY IMPROVEMENTS AS PART OF STREETCAR CONSTRUCTION:
- Underground gas work will be conducted by Duke Energy on Race Street between Liberty and Green streets; on Walnut Street near 3rd Street; and on Main Street near 4th Street.
- Storm sewer work will begin on Race Street near Findlay Street.
- Water main installation will continue on Walnut Street between 9th Street and Central Parkway.
- Traffic control conduit (tubing for electrical wires) installation will continue on Elm Street between Wade and Green streets; and on Race Street near Findlay Street.
- New sewer installation will continue on Elm Street near Green and Elder streets.
- Underground electrical work will also be conducted by Duke on 12th Street near Vine and Race streets.
- Telecommunications work will occur on Elm Street between Wade and Green streets; on Race Street between 15th and Liberty streets; and on Walnut Street near 6th Street.