For the week of November 4, 2013, the streetcar will have of a lot of highly visible progress on both the trackwork and at the Maintenance & Operations Facility site. As part of the city’s construction contract, the project is also involved with repairing public utilities. Here’s what to expect:

  • Rail delivery and installation will start on Elm Street between 14th and 15th streets.
  • Concrete base work for the track will continue on Elm Street between 12th and Wade streets.
  • Replacement of the cobblestones will take place on the east half of Elm Street.
  • Storm sewer installation, backfilling, and pavement removal for the Maintenance & Operations Facility will continue at Henry and Race streets.

 

PUBLIC UTILITY IMPROVEMENTS AS PART OF STREETCAR CONSTRUCTION:

  • Underground gas work will be conducted by Duke Energy on Race Street between Liberty and Green streets; on Walnut Street near 3rd Street; and on Main Street near 4th Street.
  • Storm sewer work will begin on Race Street near Findlay Street.
  • Water main installation will continue on Walnut Street between 9th Street and Central Parkway.
  • Traffic control conduit (tubing for electrical wires) installation will continue on Elm Street between Wade and Green streets; and on Race Street near Findlay Street.
  • Telecommunications work will occur on Elm Street between Wade and Green streets; on Race Street between 15th and Liberty streets; and on Walnut Street near 6th Street.

What’s that Giant Hole?

Posted on

You may have noticed some giant holes surrounded by wooden fencing appearing along the streetcar route. This is part of the utility relocation and improvement work being conducted by Duke Energy.

Recently, two of these giant holes were created near Washington Park on Race Street and 12th Street as Duke upgraded its power transformers. In a suburban neighborhood, these transformers are what you’d typically see up on poles, but in the city, they are buried underneath the street. Many of the old transformers in Over-the-Rhine are in need of modernization as they have been insulated with asbestos. Transformer upgrades are one of many utility improvements made possible by funding from the streetcar construction contract.

IMG_5358

Streetcar Weekly Update: October 28, 2013

Posted on

For the week of October 28, 2013, the streetcar will have of a lot of highly visible progress on both the trackwork and at the Maintenance & Operations Facility site. As part of the city’s construction contract, the project is also involved with repairing public utilities. Here’s what to expect:

  • Trackwork will continue on Elm Street between 12th and Wade streets.

 

PUBLIC UTILITY IMPROVEMENTS AS PART OF STREETCAR CONSTRUCTION:

  • Water main installation will continue on Walnut Street near Court Street.
  • Additional sewer work will take place on Race Street between Henry and Findlay streets.
  • Underground gas work will be performed by Duke Energy on Main Street near 4th Street; on Walnut Street near 3rd Street; on Race Street near Henry Street; and on Race Street between Liberty and Green streets.
  • Underground electrical work will also be performed by Duke on 12th Street between Main and Elm streets; and on Race Street near 12th Street.
  • Cincinnati Bell will perform its infrastructure work on Elm Street between Henry and Liberty streets.
  • Conduit installation (tubing for electrical wires) for traffic signals will continue on Elm Street between Wade and Green streets; and on Race Street near Findlay Street.
  • Exploratory digging for utilities will start on Main Street near 4th Street

Streetcar Weekly Update: October 21, 2013

Posted on Updated on

For the week of October 21, 2013, the streetcar will have of a lot of highly visible progress on both the trackwork and at the Maintenance & Operations Facility site. As part of the city’s construction contract, the project is also involved with repairing public utilities. Here’s what to expect:


PUBLIC UTILITY IMPROVEMENTS AS PART OF STREETCAR CONSTRUCTION:

  • New sewer installation will continue on Elm at Liberty Street.
  • New water main installation will continue on Walnut from Central Parkway to 9th Street.
  • Drains on Elm from 12th to 15th streets will continue with undercutting, proof-rolling,  & concrete base work.
  • Underground gas line work will be conducted by Duke Energy on Race Street near Liberty.
  • Underground electrical work will be conducted by Duke Energy on 12th at Vine Street; and on Race near 12th Street.
  • Cincinnati Bell will perform work on Elm between Green and Findlay.
  • Conduit installation (tubing for electrical wires) for traffic signals will continue on Elm just north of Liberty; and on Race near 12th Street. Work will resume on Race near Findlay Street.
  • Exploratory digging for utilities will continue on Elm just north of Liberty. Work will resume on Race near Findlay Street