Streetcar Update: December 20, 2013

Posted on

Yesterday, Cincinnati City Council voted to restart streetcar construction after a three week pause to audit the project. Here’s what’s coming up over the next two weeks:

Thursday, Dec. 26

  • Rail delivery on Elm Street (Findlay to McMicken). Elm Street will be closed from 11am-4pm.

Friday, Dec. 27 & Saturday, Dec. 28

  • Rail installation resumes north of Findlay Market

Monday, Dec. 30

  • Rebar installation resumes on Elm Street, north of Findlay Market.
  • Building wood forms for trackwork resumes north of Findlay Market, with concrete placement expected Jan. 2-3.
  • Work resumes on traffic signals and poles for overhead power.
  • Water main work resumes on Walnut & Main streets.

Thursday, Jan. 2

  • Excavation for trackwork resumes at Findlay & Elm streets.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s