May 2012 Construction Update

Posted on Updated on

 

This message is a guest post from the City of Cincinnati

 

Greater Cincinnati Water Works is currently in the process of replacing water mains to allow for construction to begin on the Streetcar. The focus of water main replacement at this time is along Elm Street. Race Street main replacement is scheduled to begin soon. 

Elm Street between 12th and Liberty Streets:

  • Main replacement is taking place currently on the 1400 block of Elm Street
  • Construction is right on schedule and is expected to be finished by the end of June

 Intersection of Elm and Findlay Streets:

  • Crews are in the process of laying pipe, making their way towards Henry Street
  • Work at this intersection should be completed by July 

The water main replacement that is taking place in order to further progress on the Streetcar is typical replacement that occurs annually. Water Works has coordinated the process in order to minimize costs and reduce inconveniences for Cincinnatians.

About these ads

One thought on “May 2012 Construction Update

    [...] Construction Update: Water Main Replacements Cincy Streetcar Blog: Greater Cincinnati Water Works is currently in the process of replacing water mains to allow for [...]

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s